Renovation Events and News

library renovation logo

Upcoming Events:

Spring Information Forums To Be Announced in 2019

 


Construction Update April 18, 2019:

The installation of the temporary facilities for the Library Renovation project continues to move forward. Approximately 65% of the modular units for the Library Annex (north of Library, east of DBH) and the Student Services Annex (east of the Student Services Building) have been moved to the site. The current look ahead schedule reflects:

  • April 22 – May 3, 2019 - Underground utility work will continue at the Library Annex site, in addition to interior and exterior construction of the modular units. Interior and exterior construction will continue at the Student Services Annex site.

  • April 22 – May 9, 2019 – The main walkway between the Library Service Road and the southwest corner of Bizzini Hall will be closed to widen the sidewalk per direction of the Office of State Fire Marshal. ADA access from DBH/Lot 4 to Bizzini/Quad will be redirected.

  • April 22 – June 14, 2019 – Building occupants have been emailed packing and moving instructions in preparation of the late June moves. This is a great time to start downsizing, surveying out unused equipment and packing items that are not utilized every day.

  • May 1 - 16, 2019 - modular units are scheduled to be delivered to the Library Annex, north site. Deliveries will take place between 5:00 am and 1:00 pm on these dates. Traffic will be slower in the area of Ansel Adams and Parking Lot 5 at these times.

Please use care when driving or walking near the sites, due to large equipment and trucks working in the area. We will continue to send regular e-mails to keep the campus updated of the project. In the meantime if you have concerns, please contact us at Facilities_Services@csustan.edu or extension 3623.

We appreciate all of your patience as this exciting transformation project of our campus facilities is completed.

Sincerely,

Capital Planning and Facilities Management


Construction Update April 4, 2019:

This update is a continued effort to keep the campus community apprised of project activities. The current look ahead schedule reflects:

  • April 8 – 19, 2019 - Underground utility work will continue at both the Library Annex and Student Services Annex sites, in addition to interior and exterior construction of modular units.

  • April 10 - 13, 2019 - modular units are scheduled to be delivered to the Library Annex, south site. Deliveries will take place between 5:00 am and 1:00 pm on these dates. Traffic will be slower in the area of Ansel Adams and Parking Lot 5 at these times.

  • April 15 – May 9, 2019 – The main walkway between the Library Service Road and the southwest corner of Bizzini Hall will be closed to widen the sidewalk per direction of the Office of State Fire Marshal. ADA access from DBH/Lot 4 to Bizzini/Quad will be redirected.

Please use care when driving or walking near the sites, due to large equipment and trucks working in the area. We will continue to send regular e-mails to keep the campus updated of the project. In the meantime if you have concerns, please contact us at Facilities_Services@csustan.edu or extension 3623.

We appreciate all of your patience as this exciting transformation project of our campus facilities is completed.

Sincerely,

Capital Planning and Facilities Management


Construction Update March 25, 2019:

The first phase of the Library Renovation project is in full swing! This phase includes the installation of the temporary facilities, which will be called the Library Annex (north of Library, east of DBH) and the Student Services Annex (east of the Student Services Building.) This update is a continued effort to keep the campus community apprised of project activities. The current look ahead schedule reflects:

  • March 23, 2019 - modular units being delivered to the Student Services Annex site.

  • March 25 - 29, 2019 – grading and compaction will continue at the Library Annex site, in addition to the start of underground utilities. Installation of modular units at the Student Services Annex site as well as underground utilities.

  • April 1 - 5, 2019 – Utility work continues at both sites.

  • April 6 – 10, 2019 - modular units being delivered to the south side of the Library Annex site. Interior construction continues at the Student Services Annex.

We are not expecting any roadways to be closed during these dates, but due to large equipment and trucks working in the area, please use care when driving or walking near the site. We will be sending regular e-mails to keep the campus updated of the project. In the meantime if you have concerns, please contact us at Facilities_Services@csustan.edu or extension 3623.

We appreciate all of your patience as this exciting transformation project of our campus facilities is completed.

Sincerely,

Capital Planning and Facilities Management


Academic Senate:


Renovation Schedule:

  • Spring Semester 2019 - Surge space (temporary facilities) will be placed

  • May 2019 - Design of renovated Library will be complete

  • Summer 2019 - Current building occupants will be moved into surge space

  • July 2019 - Renovation construction of existing Library will begin

  • Summer 2021 - Construction will be complete and occupants moved into renovated Library


In the news:

  • October 24, 2018 - Dean Rodriguez was interviewed by ABC 10 about the upcoming library renovation. See the video below!

Click here to see her article!